Balfour Beatty Rail AB, which operates in the rail infrastructure business in Sweden, announces today that the company has received a significant order containing three separate contracts from the Swedish Rail Administration Banverket for maintenance work of 1270 km railways in the Gothenburg area, Västra Götaland region *).
The maintenance contracts for the lines in Västra Götaland are the largest operation area that Banverket has so far contracted. The awarded contracts are on turnkey basis with functional commitment and enhanced collaboration with the infrastructure owner. The contracts duration are five years (with a scheduled project start on September 1st 2010) including an option of one year and one further option for one year. In the selection of Balfour Beatty Rail, Banverket has especially valued good reference ratings for ongoing maintenance contracts and how Balfour Beatty Rail has planned for the maintenance works, preventive andcorrective maintenance of track, OHL, Signalling and Telecom, accident management and snow clearance.
The total order value for the new contracts are approximately 970 MSEK (92 MEUR).
Today, Balfour Beatty Rail AB has several ongoing contracts for railway maintenance works in Sweden. Our objective is to deliver a complete service commitment, which extends over the entire lifecycle of the railway plant. Current ongoing maintenance contracts includes; Mälar Line (280 km), Holmsund-Vännäs-Bastuträsk (170 km) and Österlen lines (180 km)
Balfour Beatty Rail AB’s, Head of Business Unit Maintenance, Carola Alzén commented, "With these contracts, we will demonstrate that we are a reliable maintenance contractor. We have now a very important process ahead of us in establishing new site offices and recruiting over 100 new employees. I am looking forward in welcoming so many new employees", concludes Carola Alzén.
Balfour Beatty Rail AB's Managing Director Magnus Jonasson said: "The award of these areas are together by far the largest order volume we have received under the company's history and we are delighted that Banverket has chosen us as a contractor to maintain and improve railway performance of the lines in Västra Götaland. Our objective will be to reduce delays for travellers and for the freight traffic with efficient and cost-effective railway maintenance. In achieving the delivery of a complete service commitment we will measure our performance by our client’s success" concludes Magnus Jonasson.
Finally, Balfour Beatty Rail's significant order intake during 2009 has generated an increased market share for the company in Swedish railway construction and maintenance. We are thereby strengthening our position as the leading privately owned railway contractor in Sweden which has been a long-term strategy for the Balfour Beatty Group.
*) Information in short;
Contract 1 Västra Götaland Göteborg
Totalling: 382 km
Bdl.601 Göteborgsnärställverksområde
Bdl. 602 Sävenäs rangerbangård
Bdl. 603 Hamnbanan
Bdl. 612 Partille-Alingsås (Västra Stambanan)
Bdl. 624 Göteborg Kville – Stenungsund (Bohusbanan)
Bdl. 626 Göteborg, Mölndal, Kungsbacka (Västkustbanan)
Bdl. 635 Göteborg Marieholm – Älvängen (Norge/Vänerbanan m Nordlänken)
Contract 2 Västra Götaland Väst
Totalling: 351 km
Bbl.621 Uddevalla – Strömstad (Bohusbanan)
Bbl 624 Stenungsund – Uddevalla (Bohusbanan)
Bbl 623 Smedberg – Lysekil (Bohusbanan, Stråk 72 Munkedal-Lysekil)
Bbl 635 Öxnered – Älvängen (Norge/Vänerbanan med Nordlänken
Bbl 651 Uddevalla – Öxnered (Älvsborgsbanan)
Bbl 652 Öxnered – Håkantorp (Älvsborgsbanan)
Bbl 666 Alvhem– Lilla-Edet (Norge/Vänerbanan med Nordlänken, Stråk 74)
Contract 3 Västra Götaland Öst
Totalling: 540 km
Bbl 512 Laxå – Falköping (Västra Stambanan)
Bbl 552 Gårdsjö – Håkantorp Stråk 75 (Har inget ban namn)
Bbl 611 Falköping – Alingsås (Västra Stambanan)
Bbl 652 Håkantorp – Herrljunga (Älvsborgsbanan)
***
About Balfour Beatty Group: The international engineering, construction, service and investement group, Balfour Beatty employs 53 000 employees. The full-year revenue for 2008 was 9.4 billion GBP. The part of the group which operates the rail infrastructure solutions, Balfour Beatty Rail, has its headquarters in the UK and is an international railway group with activities primarily in Europe, USA and Asia. The Swedish company, Balfour Beatty Rail AB, with headquarters in Västerås employs approximately 300 employees and had a turnover of 900 million SEK in 2008.
END
Contact details:
Magnus Jonasson, Managing Director
Balfour Beatty Rail AB Visiting address: Nätverksgränd 7 Box 413 SE-721 08 Västerås, Sweden Tel: +46 21 154401 E-mail: magnus.jonasson@bbrail.com www.bbrail.se |