The scope of work included engineering, procurement, installation, test and commissioning of following subsystems:
- 100 km overhead transmission line 150 kV
- 100 km double track 2x25 kV AC overhead contact line
- 7 km double track 3 kV DC overhead contact line
- 2 sub-stations 150 / 25 kV AC/AC
- 9 autotransformer stations 2x25 kV AC
- Remote Control System for Power Supply to whole section
The Rome-Naples high speed line was completed on 10 September 2005 and is in operations since January 2006. |