You are here: // Capabilities // Asset Management

Asset Management

  OHLE and Power Supply Infrastructure Maintenance
 Country  Malaysia
 Customer  KTMB
 Value  RM 42.7 million
 Order Date  8/1996
 Completion Date  4/2007
OHLE and Power Supply Infrastructure Maintenance
KTMB contracted out the maintenance of the then newly completed and commissioned electrification infrastructure to Balfour Beatty Rail Sdn Bhd.  This maintenance project has been renewed for the four terms.  The scope of works consists of the maintenance of the 25kV electrification systems including incident and accident rectification of the overhead catenary system, feeder, track sectioning, tie breaker stations and SCADA installed.

<< back